RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD.

 

Annual Plan 2007-08 (Revised)

 

I.          XI PLAN OUTLAYS

 

1.         The Planning Department, Govt. of Rajasthan vide letter no.F.17(23)Plan/Gr IV/2006 dated 24.11.2006 had informed total revised tentative outlay for XI Five Year Plan for all power sector companies as Rs.25205 crores.   This outlay is inclusive of Rs.2000 crores towards Transition support (FRP) from State Govt.  Thus the outlay for capital works remained as Rs.23205 crores. Out of total of Rs.23205 crores outlay for capital works intimated by Planning Department for all five power sector companies, an outlay of Rs.4600 crores was fixed for RVPN.  The year wise break-up of Rs.4600 crores is as under:

Rs.in crores

 

2007-08

2008-09

2009-10

2010-11

20011-12

Total

RVPN

 

 

 

 

 

 

Transmission

612.00

815.00

1113.00

1010.00

970.00

4520.00

Generation (Shared Generating Projects)

10.00

10.00

20.00

20.00

20.00

80.00

   Total

622.00

825.00

1133.00

1030.00

990.00

4600.00

 

2          Besides above the State Government will provide Rs.2000 crores as transition cash support towards FRP in XI Five Year Plan to RVPN, which will be eventually passed on to Discoms.

 

II.         ANNUAL PLAN 2007-08 (Revised)

 

1.         Introduction

 

1.1.      The Planning Department Government of Rajasthan vide letter no.F.17 (23) Plan/ Gr.IV/ 2006 dated 24.11.2006 had intimated tentative outlays for Annual Plan

2007-08 of Rs.4659 crores (including Rs.400 crores of Transition support) for all 5 companies of Power Sector.

 

The matter was discussed with Finance Deptt., GoR for enhancement of this outlay to Rs.5318 crores which was agreed and later on indicated in the Booklet for Draft XI Five Year Plan for the State.  Out of outlay of Rs.5318 crores, Rs.622 crores have been allotted to RVPN for capital works and Rs. 400 crores as Transition Support. The proposals of XI Five Year Plan and Annual Plan 2007-08 were sent to Planning Department, GoR, vide letter no. 1232 dt. 14.12.2006.

 

1.2              Recently the Secretary (Plan), GoR vide letter no.F.10(11)Plan/ Gr.V/07 dated 19.5.07 has intimated the Annual Plan 2007-08 Budgeted outlay for Power Sector companies as under:

(Rs. In lacs)

S.No.

 Particulars

Budgeted Outlay 2007-08

1

Raj. Rajya Vidyut Utpadan Nigam Ltd.

274100.00

2

Raj. Rajya Vidyut Prasaran Nigam Ltd.

57400.00

3

Discom Jaipur

41300.01

4

Discom Jodhpur

41000.01

5

Discom Ajmer

49200.01

6

FRP

28800.00

7

FRP-Transition Support

40000.00

 

 Total

531800.03

 

            There is no change in overall outlay of Power Sector companies, therefore the outlay for capital works of RVPN remains same i.e. Rs.622 crores.  Besides this Rs.400 cores towards Transition support shall also be given to RVPN, which will be eventually passed on to Discoms.

 

1.3       The headwise breakup of Rs. 622 crores for capital works is as under:

(Rs.in crores)

S.No.

Head

Plan Outlay 2007-08 (Proposed)

I.

Generation (Shared Generating Projects)

 

 

1. S&I Preliminary Exps.

1.00

 

2. Renovation & Modernization/ Uprating of shared generating stations.

 

 

a.       Uprating of Bhakra Left Bank

 

b.       Other Capital works of BBMB

  

    9.00

 

Total (I)

10.00

II

Transmission:

 

 

1. On going & New works

552.00

 

2. EAP works/ World Bank Loan

48.00

 

3. Counterpart for 2

12.00

 

Total-(II)

612.00

 

Grand Total ( I + II)

622.00

 

2.         Resources

 

The details of resources envisaged for financing above outlay of Rs.622 crores is as under:

 

A.         Direct                                      -           (Rs. In crores)

 

1.         LIC                                           -           100.00

2.         REC                                        -           236.00

3.         PFC & Commercial Banks     -           113.00

 

            Total                                                    449.00

 

B.         Through State Government

 

1.         World Bank (EAP)                  -           48.00

2.         State Government Equity        -           125.00

            (Including Rs.12 crores matching-    

            amount for EAP)

 

            Total                                                    173.00

Total  (A+B)                             622.00

 

 

3.         Works Position

 

            The detailed works position for RVPN is given as under:

 

 

 

 

 

 

 

3.1       Generation (Shared Generating Projects)

 

3.1.1    Survey & Investigation of New Projects and Preliminary Expenses

 

            A provision of Rs.1.00 crores has been kept during the year 2007-08 for making payment for S&I Work and for preliminary expenses for interstate new projects. This provision can be utilized for any expenses towards Environment Impact Assessment Studies and other departmental works as per terms and conditions of Central Water Commission for Chambal Development Plan (Phase-II) (Rahu Ghat Hydro Electric Project)

 

3.1.2. Bhakra Beas Complex

           

            A total provision of Rs. 9.00 crores for up rating of Bhakra Left Bank,  and for other Capital Works of BBMB has been kept   during the year 2007-08. This provision is for the Rajasthan’s Share in Modernization works. 

 

3.2.      Transmission

 

3.2.1.   A provision of Rs.612 crores has been kept during the year 2007-08 mainly for ongoing EHV normal development works and  evacuation system of Dholpur GTPS (Phase-I), Chhabra TPS (Stage-I, Phase–I), Suratgarh TPS (Unit-6), Giral LTPS (Phase-I & II), Wind Farm Project, Barsingsar LTPS and associated Transmission system. The construction of 400kV Dholpur-Heerapura line for Evacuation of Dholpur GTPS and construction of 400kV Ratangarh-Merta line are in full swing presently and will be completed in 2007-08.  The work of construction of 400kV GSS at Bhilwara and Hindaun with associated 400kV lines under evacuation of Chhabra TPS  and 400kV STPS-Bikaner line with 400kV S/S at Bikaner under evacuation of STPS (Unit-6) will be started in 2007-08. These works are scheduled to be completed in 2008-09, matching with commissioning of Generating Projects.  The Evacuation systems of Jalipa & Kapurdi (Raj West) and Wind Farm Generation in Jaisalmer/ Barmer area were approved in 2006-07 and have been  included in Annual Plan 2007-08 as new start. Besides above evacuation system of Chhabra TPS (Stage-I, Phase-II) has also been approved recently & has been included in Annual Plan 2007-08 as new start with token provision.

 

3.2.2.   During 2006-07, schemes for construction of 4 Nos. of 220kV GSS at Indira Gandhi Nagar, Jaipur (Hybrid S/S), Baran (evacuation of Chhabra TPS), Sanchore & VKI (Jaipur) and 5 Nos. of 132kV GSS at Dalot (Chittorgarh), Sata (Barmer), Galifa (Jalore) PWD Bunglow  (Jaipur-Hybrid S/S) and Sapotra (Karauli) were approved.  These schemes have been included in Annual Plan for execution.  220kV GSS at Sanchore and 132kV GSS at Satta and Galifa have been approved for work of Narmada Canal Project.  Besides above, inter-connection lines for 400kV GSS of PGCIL at Kankroli & Kota have also been approved and included in  Annual Plan.  With this presently, 3 Nos. of 400kV GSS,   9 Nos. of 220kV GSS and 22 Nos. of 132kV GSS are under execution.  Most of the 220kV & 132kV Sub-Stations which are already under construction are scheduled to be commissioned during 2007-08. In addition to above recently one 220kV GSS at Kishangarh (Ajmer) & 15 Nos. of 132kV Schemes for construction of 132kV GSS have been approved.  The same have also been included In Annual Plan 2007-08 as new start.  These new GSS shall be commissioned in 2007-08 to  2009-10.  Some more new works related to Evacuation system of forth coming generating projects, 220kV new sub-stations as per load requirement and 132kV new Sub-Stations as per requirement of Discoms may be included in Annual Plan 2007-08.

 

 

3.2.3.   With the above works in sight the following physical targets are proposed for the transmission works to be undertaken as per plan outlay.

 

S. No.

Works

Unit

Target (Proposed) for the Year 2007-08

i.

Transmission :

-  400 kV Lines

- 220 kV Lines

- 220 kV Substations

-220kV Substation

- 132 kV Lines

- 132 kV Substations

- 132 kV Substations

 

kM.

kM

MVA

Nos.

kM

MVA

Nos.

 

485

400

300

3

300

300

12

ii

Augmentation

MVA

600

 

3.2.4.   The scheme wise plan provisions are shown in Annexure-A.

 

4.         Government support during 2007-08

 

4.1.      As per announcements made by the Chief Minister and directions from the Chief Minister’s secretariat, 220kV GSS at Barmer,  new 132kV GSS at Merta Road &  Roon (Distt. Nagaur), Bakani (Distt. Jhalawar), Baseri (Distt. Dholpur), Jhadol (Distt. Udaipur), Shahpura (Distt.-Bhilwara), Khatu Shyamji have been commissioned during 2006-07. Left over works of these GSS all be completed during 2007-08 Besides these 132kV GSS at Koodan (Distt.Sikar), Parewara (Churu), Ramseen (Distt. Jalore) and  Dalot (Distt. Chittorgarh) are under execution which shall  be commissioned during 2007-08 & 2008-09. Some more new 132kV schemes for construction of 132kV GSS at Sapotra (Distt. Karauli), Manohar Thana (Distt. Jhalawar), Jasrasar, Dulchasar & Riri (Distt.-Bikaner) and Rawatsar (Dist.  Hanumangarh) have also been announced by Chief Minister.  The work on all these schemes shall be started during 2007-08 and will be completed during 2007-08 and 2008-09. The work on various evacuation system for new power project viz. 2x250 MW Chhabra TPS Stage-I, Phase-I, STPS Unit 6 etc. will be in full swing and is scheduled to be completed in 2008-09. Extra funds shall be required to execute these schemes.

 

4.2       The scheme for construction of 220kV GSS at Neemarana alongwith augmentation work at existing 220kV & 132kV GSS in National Capital Region is being executed through loan assistance from National Capital Region Planning Board (NCRPB).  The 30% of scheme cost is to be met from Plan fund of RVPN.  The number of new schemes and evacuation schemes shall be executed by taking loan assistance from Financial Institutions viz. PFC, REC, Commercial Banks etc. The counter part fund for such loan assistance is required to be met from Plan fund and assistance from State Govt. is required to meet such demand. Similarly as per terms of World Bank for loan assistance, 20% of the total cost is to be funded by Govt. of Rajasthan.  For all these works an Equity support of Rs.125 crores has been agreed by State Government for Annual Plan 2007-08.

 

********